Procurement
| Name | Description | Effective Date | Due Date | Time | ||
| RFQ 2009-01 | 2009 ON-CALL ENGINEERING SERVICES REQUEST FOR QUALIFICATIONS | Sept. 20, 2009 | Oct. 15, 2009 | 2:00pm est | ||
| CWF 2009-04A | Yale/Trumbull Phase 1B; Lock & Canal Streets | November 9, 2009 | December 8, 2009 | 10:00 AM | ||
| RFQ 2009-01 Responses | Response to Questions | October 7, 2009 | ||||
| CWF 2009-04B | Yale/Trumbull Phase 1B; Prospect/Sachem/Canal/Mansfield/ Compton Streets | Jan. 7, 2010 |
Feb. 4, 2010 |
10:00 AM | ||
| CWF 2009-04B | Yale/Trumbull Phase 1B - Addendum 1 | Jan. 22, 2010 | Feb. 4, 2010 | 10:00 AM | ||
| CWF 2009-04B | Yale/Trumbull Phase 1B -Addendum 2 | Jan. 29. 2010 | Feb. 4, 2010 | 10:00 AM | ||
| RFQ 2010-01 | Wind Generated Electric Turbine Invitation | Jan. 11, 2010 | Feb. 18, 2010 | 2:00 PM | ||
| RFQ 2010-01 | Wind Generated Electric Turbine RFQ | Jan. 11, 2010 | Feb. 18, 2010 | 2:00 PM | ||
| RFQ 2010-01 | Wind Generated Electric Turbine RFQ Deadline Extension | Feb. 3, 2010 | March 11, 2010 | 2:00 PM | ||
| RFQ 2010-01 RFQ Picture | Wind Generated Electric Turbine RFQ Questions & Answers | Feb. 4, 2010 | March 11, 2010 | 2:00 PM | ||
| RFQ 2010-01 RFQ Photo 2 | Wind Generated Electric Turbine RFQ Questions & Answers | Feb. 24, 2010 | March 11, 2010 | 2:00 PM | ||
| SSR 2008-01 | Forbes & Stiles Sewer Relocation | Feb. 4, 2010 | Feb. 25, 2010 | 10:00 AM | ||
| SSR 2008-01 | Forbes & Stiles Addendum 1 | Feb. 12, 2010 | Feb. 25, 2010 | 10:00 AM | ||
| SSR 2008-01 | Forbes & Stiles Addendum 2 | Feb. 22, 2010 | Feb. 25, 2010 | 10:00 AM | ||
| SSF 2008-07 | Pump Station By-Pass Installation | June 3, 2010 | July 1, 2010 | 10:00AM | ||
| SSF 2008-07 | PS By-Pass Addendum #1 | June 15, 2010 | July 1, 2010 | 10:00AM | ||
| SSF 2009-07 | Portable Solids Handling Trash Pump | June 17, 2010 | July 20, 2010 | 10:00AM |